Vernazza Autogru has carried out structural work to disassemble the coal pipeline of the former power station in Vado Ligure. It is a historical step for the industrial reconversion of these areas and the launch of Vernazza Autogru new logistics hub.
Three cranes were used for this specific work: two telescopic cranes, Demag AC 800 and Liebherr LTM 1300 6.1, and a crawler crane Demag CC 3800.
The pipeline was dismantled into sections of 20 m length and a diameter of 4.5 m.